HD Korea Shipbuilding & Offshore Engineering’s subsidiary increased its share of the Boryeong power-station coal-yard enclosure contract by ₩100m to ₩333bn. The revision is only 0.03% of the contract value. The filing says the order equals 8.5% of HD Hyundai Samho’s 2020 standalone revenue. It equals about 1.1% of HD KSOE’s FY2025 consolidated revenue. Work began in September 2021 and is scheduled to finish on August 31, 2027. The price and timetable may change with design or project conditions.
Every figure is taken from HD Korea Shipbuilding & Offshore Engineering Co., Ltd.'s own DART filings and matched on IFRS account codes, so a line holds across years where the Korean wording changed.