CS Wind signed a ₩151.0bn wind-tower supply contract with Vestas American Wind Technology. The US order equals 5.2% of FY2025 consolidated revenue. Deliveries run from September 4, 2026, through July 2, 2027. The customer provides no advance payment. Payment falls five days after the month-end following 60 days from delivery. The final delivery date and contract amount may change through discussions with the customer.
Every figure is taken from CS Wind Corporation's own DART filings and matched on IFRS account codes, so a line holds across years where the Korean wording changed.