Ipark Hyundai Development raised its Seonghwang-Wonseong redevelopment contract from ₩338.15bn to ₩462.92bn. The revised amount equals 11% of FY2019 consolidated revenue. The Cheonan project covers 1,684 apartments. Construction now lasts 35 months from actual commencement, up from 31 months. Calendar start and completion dates remain blank. Approvals and contract conditions can change the project, price or schedule.